Only for GDS by GDS - India Post

Only for GDS by GDS - India Post

Monday 20 August 2018

GDS Pay Arrears - Dissatisfaction

Attention to all GDS :


Arrear calculation : Received arrears are not according to Kamalesh Chandra Committee Recommendations.

As per Report:
One BPM with a scale of 2745/-
As per the recommendations , he will be placed in Rs.12,000 (level 1 BPM scale & 4 hours ) .

But before implementation of Report his working hours is only 3 hours.

So, for arrear calculation , one must have considered the scale ( actual working hours i.e; 3 hours ) for the period between 1.1.2016 and date of effect is exactly Rs.9,000/-.

So, Rs.9,000- Basic+DA as on month will be the arrears for GDS.

But, DoP modified the previous arrears calculation method by receiving the order from PMO.

PMO directed DoP to modify and submit re calculation of arrears procedure.

As per present implemented orders of GDS Arrears , DoP issued following procedure which is illegal
Basic pay ×2.57 - Basic +DA.
2.57 fitment factor is only for finalising new wage scales. It is not applicable to arrears.

Arrears calculation is clearly related to new wage scales - basic+DA.

Due to irregular and illegal formula applied by DoP, nearly Rs.3,100 crores loss to GDS.

This issue can be challenged in the Court of Law.

This article written by 
Ch.Laxmi Narayana, Circle Secretary-AP, NUGDS.

No comments: